China Factory Project Cases
China reference 01 · Electronics and intelligent manufacturing
Technology Industrial Park Phase I in East China
A planned industrial park in Jiangsu on approximately 22 mu of land, with approximately 35,100 m² of low-carbon factory buildings and R&D and office space, combining manufacturing and research functions.
- Development approach
- New factory buildings for Phase I of an industrial park.
- Key facilities
- Low-carbon factory buildings, R&D and office space, parking and ancillary facilities.
- Key site requirements
- Industrial land in Suzhou, Jiangsu; coordinated provision for manufacturing workshops and R&D offices.
- Planned investment and schedule
- Total investment: RMB 125 million. Construction period: 3 years.
- Comparable applications
- Electronics industrial parks; R&D and manufacturing bases; low-carbon standard factory buildings.
China reference 02 · Semiconductors and electronic equipment
Semiconductor Cleaning Equipment Manufacturing Base in East China
Planned use of approximately 35,100 m² of factory, R&D and office space in Jiangsu for semiconductor cleaning equipment production, with capacity for approximately 200 cleaning, wet-etching and related machines per year.
- Development approach
- Lease of factory premises in an industrial park and installation of production lines.
- Key facilities
- Automated semiconductor cleaning equipment production line, R&D offices and testing areas.
- Key site requirements
- Existing factory premises in Suzhou, Jiangsu; suitability for equipment installation and clean production.
- Planned investment and schedule
- Total investment: RMB 80.8815 million. Construction period: 2 years.
- Comparable applications
- Semiconductor equipment factories; wet-process equipment production bases; precision equipment manufacturing.
China reference 03 · Advanced materials and resource recycling
Recycled Graphite Materials Production in Northwest China
Planned recycled graphite processing facilities in Ningxia on approximately 20 mu of land, with approximately 11,500 m² of buildings and dedicated raw material, production, finished goods and testing areas.
- Development approach
- Construction or conversion of facilities for recycled material production.
- Key facilities
- Raw material, production, finished goods and laboratory testing areas.
- Key site requirements
- Industrial land in Ningxia; provision for feedstock collection, processing and finished goods transport.
- Planned investment and schedule
- Total investment: RMB 70 million. Construction period: approximately 1 year.
- Comparable applications
- Recycled graphite factories; carbon material production bases; higher-value utilization of industrial solid waste.
China reference 04 · Additive manufacturing and advanced materials
Industrial Park for Recycled 3D Printing Materials in South China
A planned park in Guangxi on approximately 137.87 mu, with approximately 73,200 m² of buildings for main workshops, R&D offices, logistics, finished goods and utilities.
- Development approach
- New industrial park for recycled 3D printing materials.
- Key facilities
- Main workshops, finished goods and logistics areas, research offices and wastewater treatment facilities.
- Key site requirements
- Hezhou, Guangxi; integrated planning of production, logistics and utilities.
- Planned investment and schedule
- Total investment: RMB 260 million.
- Comparable applications
- Additive manufacturing parks; 3D printing material factories; recycled material processing bases.
China reference 05 · Semiconductors and electronic equipment
Semiconductor Epitaxy Equipment R&D and Industrialization in North China
A planned multipurpose production building in Beijing, with MOCVD equipment assembly lines and R&D facilities to support commercial manufacturing of high-precision epitaxial growth equipment.
- Development approach
- New production building and assembly lines.
- Key facilities
- Metal-organic chemical vapor deposition (MOCVD) equipment assembly lines, R&D areas and equipment commissioning space.
- Key site requirements
- Shunyi Comprehensive Bonded Zone, Beijing; conditions suitable for precision equipment R&D and manufacturing.
- Planned investment and schedule
- Total investment: RMB 483 million. Total Phase I construction period: 26 months.
- Comparable applications
- MOCVD equipment factories; semiconductor equipment industrialization; advanced equipment R&D and manufacturing bases.
China reference 06 · Cold chain equipment and logistics facilities
Cold Chain Equipment R&D and Manufacturing Base Phase I in North China
A planned development in Hebei on approximately 31,800 m² of land, with approximately 17,600 m² of R&D workshop space, pilot production lines for cold chain equipment, experimental platforms and utilities.
- Development approach
- New R&D workshop buildings and pilot production lines.
- Key facilities
- Two R&D workshop buildings, experimental platforms and a cold chain equipment pilot line.
- Key site requirements
- Zhangjiakou Economic Development Zone, Hebei; suitable buildings, utilities and cold chain testing conditions.
- Planned investment and schedule
- Total investment: RMB 150 million. Construction period: approximately 2 years.
- Comparable applications
- Refrigeration equipment factories; cold chain equipment R&D and manufacturing bases; equipment production for cold storage facilities.
China reference 07 · Semiconductor industry infrastructure
Standard Factory Buildings and Energy Infrastructure for the IC Industry in North China
Planned standard factory buildings, R&D buildings and connecting corridors in Beijing for integrated circuit (IC) equipment and component manufacturers, supported by heating and energy station facilities.
- Development approach
- New standard factory buildings for the IC industry and associated energy infrastructure.
- Key facilities
- R&D buildings, standard factory buildings, connecting corridors, an energy station and heating systems.
- Key site requirements
- Beijing Economic-Technological Development Area; reliable energy supply and the specific requirements of IC manufacturing premises.
- Planned investment and schedule
- Factory building project: approximately RMB 386 million. Associated heating project: approximately RMB 4.64 million.
- Comparable applications
- Standard factory buildings for the IC industry; semiconductor industrial parks; energy infrastructure for cleanroom facilities.
China reference 08 · Pharmaceutical manufacturing
Intelligent Softgel Production Line
Review of production equipment, utilities and energy requirements for a softgel production line and its energy-saving scheme. The underlying document is an energy conservation report and does not independently establish that new factory buildings are proposed.
- Development approach
- Production line development and energy provision within an existing pharmaceutical plant.
- Key facilities
- Intelligent softgel production line and associated utilities.
- Key site requirements
- An existing pharmaceutical site; workshop compatibility and energy supply are the principal considerations.
- Comparable applications
- Pharmaceutical dosage-form production lines; softgel workshop conversions; energy efficiency upgrades at pharmaceutical factories.
China reference 09 · Food and biomanufacturing
Alternative Protein Industrial Base in East China
A planned industrial base in Shanghai on approximately 50 mu, integrating production, R&D and ancillary facilities for alternative protein products.
- Development approach
- New alternative protein industrial base.
- Key facilities
- Food production, R&D and ancillary facilities.
- Key site requirements
- Planned site in Jinshan, Shanghai; coordinated food production, R&D and logistics requirements.
- Planned investment and schedule
- Total investment: approximately RMB 475 million. Construction period: approximately 1 year.
- Comparable applications
- Alternative protein factories; plant-based protein food production bases; innovative food industrial parks.
China reference 10 · Environmental equipment and advanced materials
Air Purification Equipment and Environmental Material Production Base in South China
Planned Phase I of a production base in Guangdong for air purification equipment and new environmental materials, including production space, equipment and supporting facilities.
- Development approach
- New Phase I production base.
- Key facilities
- Air purification equipment and environmental material production areas and associated infrastructure.
- Key site requirements
- Industrial land in Guangdong; coordination of equipment manufacturing, material production and environmental facilities.
- Planned investment and schedule
- Phase I investment: approximately RMB 123 million. Expected construction period: 3 years.
- Comparable applications
- Air purification equipment factories; environmental material production bases; environmental equipment industrial parks.
China reference 11 · New energy and energy storage
Energy Storage Battery Pack Production in East China
A planned environmentally oriented energy storage battery pack project in Shandong, covering manufacturing, assembly, testing and ancillary facilities.
- Development approach
- Leased factory premises with phased installation of production lines.
- Key facilities
- Energy storage battery pack production lines, testing facilities, offices and staff amenities.
- Key site requirements
- Existing factory premises in Dongying, Shandong; checks on power supply, fire safety and equipment installation conditions.
- Planned investment and schedule
- Overall investment: RMB 300 million. Phase I: approximately RMB 79.8259 million, with a 5-month construction period.
- Comparable applications
- Energy storage battery pack factories; battery system integration bases; new energy equipment manufacturing.
China reference 12 · Intelligent equipment
Industrial Robot R&D and Industrialization
Study of the R&D, assembly, manufacturing and operating premises required to develop industrial robots and bring them into commercial production.
- Development approach
- Development of premises for robot R&D and industrialization.
- Key facilities
- R&D, assembly and product testing areas.
- Key site requirements
- Integration of R&D and manufacturing, and suitable equipment assembly conditions.
- Planned investment and schedule
- Total investment: RMB 50 million.
- Comparable applications
- Industrial robot factories; intelligent equipment manufacturing bases; robot assembly centers.
China reference 13 · Food and agricultural processing
Agri-Food Technology R&D and Manufacturing Headquarters in East China
A planned agri-food technology R&D headquarters and industrial base integrating research, manufacturing, offices and supporting functions.
- Development approach
- New R&D headquarters and agri-food technology base.
- Key facilities
- R&D platform, manufacturing center, supply chain center and intelligent central kitchen.
- Key site requirements
- Approximately 85 mu of planned land; combined requirements for food production, R&D and cold chain distribution.
- Planned investment and schedule
- Total investment: approximately RMB 1.013 billion. Construction period: 24 months.
- Comparable applications
- Agri-food technology bases; food R&D and manufacturing headquarters; agricultural processing industrial parks.
China reference 14 · Mining and resource recycling
Integrated Utilization of Lead Zinc and Silver Tailings in Northern China
Planned tailings resource recovery facilities in Inner Mongolia, with areas for raw material treatment, processing and environmental infrastructure.
- Development approach
- Development of tailings resource recovery facilities.
- Key facilities
- Tailings treatment, production and processing, and environmental facilities.
- Key site requirements
- A mining area in Inner Mongolia; availability of tailings, transport access and environmental conditions.
- Planned investment and schedule
- Total investment: approximately RMB 24.9639 million. Construction period: approximately 3 months.
- Comparable applications
- Tailings utilization plants; non-ferrous metal solid waste treatment bases; mining resource recycling projects.
China reference 15 · Pharmaceutical manufacturing
Equipment Renewal in a Traditional Chinese Medicine Pill Workshop in North China
Replacement of secondary packaging equipment in an existing traditional Chinese medicine small-pill workshop, representing an upgrade within an operating pharmaceutical factory.
- Development approach
- Equipment renewal within an existing workshop.
- Key facilities
- Pill secondary packaging equipment and associated installation and commissioning provisions.
- Key site requirements
- An existing pharmaceutical factory; integration of new equipment with the workshop and production process.
- Planned investment and schedule
- Total investment: RMB 3.5 million. Construction period: 7 months.
- Comparable applications
- Traditional Chinese medicine formulation workshop upgrades; pill packaging lines; pharmaceutical factory equipment renewal.
China reference 16 · Pharmaceutical manufacturing
Pharmaceutical Granule Packaging Line in North China
A planned sachet packaging line for pharmaceutical granules within an existing plant, including packaging equipment and workshop facilities.
- Development approach
- Packaging line installation within an existing factory.
- Key facilities
- Granule sachet packaging equipment and workshop facilities.
- Key site requirements
- An existing pharmaceutical factory; coordination between removal of old equipment and trial operation of the new line.
- Planned investment and schedule
- Investment: RMB 2.6 million. Construction period: 8 months.
- Comparable applications
- Pharmaceutical granule packaging lines; intelligent pharmaceutical workshop upgrades; pharmaceutical packaging bases.
China reference 17 · Semiconductors and electronic equipment
IC Transfer Equipment Industrialization in North China
Planned premises and production equipment for the industrialization of IC transfer equipment. Feasibility and energy conservation documents for the same project are presented as one case.
- Development approach
- Development of manufacturing facilities for IC transfer equipment.
- Key facilities
- Precision equipment manufacturing and assembly facilities, with associated energy efficiency measures.
- Key site requirements
- Beijing; suitable factory premises and energy supply for precision equipment manufacturing.
- Planned investment and schedule
- Total investment: approximately RMB 328 million.
- Comparable applications
- IC transfer equipment factories; semiconductor equipment manufacturing bases; precision equipment industrialization.
China reference 18 · Pharmaceutical manufacturing
Smart Packaging Upgrade for Calcium Supplement Formulations in North China
Upgrade of an intelligent granule formulation packaging line in an existing pharmaceutical factory, including packaging equipment and associated production facilities.
- Development approach
- Smart packaging line upgrade within an existing pharmaceutical plant.
- Key facilities
- Granule formulation packaging equipment and workshop facilities.
- Key site requirements
- An existing pharmaceutical factory; production line integration and suitable pharmaceutical manufacturing conditions.
- Planned investment and schedule
- Total investment: RMB 19 million. Construction period: 1 year.
- Comparable applications
- Pharmaceutical packaging line upgrades; granule formulation workshop conversions; intelligent pharmaceutical factories.
China reference 19 · Grain processing and storage
Grain Storage Facilities in East China
Planned grain storage facilities and multistorey warehouses in the Yangtze River Delta, supporting storage, stock turnover and site infrastructure. Two report versions have been consolidated into one case.
- Development approach
- New grain storage facilities.
- Key facilities
- Multistorey warehouses, loading and unloading facilities, and storage and transport infrastructure.
- Key site requirements
- Yangtze River Delta; grain transport, warehouse turnover and moisture protection requirements.
- Planned investment and schedule
- Construction investment: approximately RMB 371 million.
- Comparable applications
- Grain storage bases; multistorey grain warehouses; warehouse infrastructure for agricultural processing parks.
China reference 20 · Pharmaceutical manufacturing
Integrated Preprocessing Line for Traditional Chinese Medicinal Materials in North China
An integrated preprocessing line for root and rhizome medicinal materials within an existing pharmaceutical factory, linking raw material treatment, production and workshop facilities.
- Development approach
- Upgrade of a preprocessing line in an existing traditional Chinese medicine plant.
- Key facilities
- Integrated root and rhizome preprocessing line and installation and commissioning space.
- Key site requirements
- An existing pharmaceutical factory; integration of raw material treatment with downstream processes.
- Planned investment and schedule
- Investment: approximately RMB 3.9 million. The construction period is not shown because the report contains inconsistent statements.
- Comparable applications
- Traditional Chinese medicine preprocessing workshops; medicinal material processing lines; pharmaceutical factory upgrades.
China reference 21 · Pharmaceutical manufacturing
Traditional Chinese Medicine Pill Production Line in North China
A planned small-pill production line within an existing multipurpose pharmaceutical building, involving installation of a new line in an existing structure.
- Development approach
- New production line within an existing building.
- Key facilities
- Small-pill production equipment and workshop alterations.
- Key site requirements
- An existing multipurpose building; verification of floor load capacity and process flows.
- Planned investment and schedule
- Construction period: approximately 1 year.
- Comparable applications
- Traditional Chinese medicine pill lines; in-plant pharmaceutical production line conversions; proprietary Chinese medicine workshops.
China reference 22 · Pharmaceutical manufacturing
Green and Intelligent Pharmaceutical Factory Pilot in North China
A pilot upgrade of an existing pharmaceutical factory, integrating production systems, energy efficiency improvements and digitalization.
- Development approach
- Green and intelligent upgrading of an existing pharmaceutical plant.
- Key facilities
- Digital production systems, energy-saving systems and workshop infrastructure.
- Key site requirements
- An existing pharmaceutical factory; coordination of upgrades while maintaining production continuity.
- Planned investment and schedule
- Investment: approximately RMB 7 million.
- Comparable applications
- Green pharmaceutical factories; intelligent pharmaceutical workshops; pharmaceutical plant energy efficiency retrofits.
China reference 23 · Building materials manufacturing
Ready-Mixed Concrete Batching Plant
A planned ready-mixed concrete batching plant with associated production, storage, transport and environmental facilities.
- Development approach
- New ready-mixed concrete batching plant.
- Key facilities
- Mixing equipment, aggregate storage and handling facilities, and dust control systems.
- Key site requirements
- Aggregate supply transport, concrete delivery access and environmental separation distances.
- Planned investment and schedule
- Total investment: approximately RMB 28.6142 million.
- Comparable applications
- Ready-mixed concrete batching plants; concrete factories; building material production bases.
China reference 24 · Additive manufacturing and advanced materials
Additive Manufacturing Production Base
A planned additive manufacturing base with 3D printing production space, equipment and ancillary facilities.
- Development approach
- New additive manufacturing production base.
- Key facilities
- 3D printing equipment, factory buildings and auxiliary facilities.
- Key site requirements
- Suitable equipment installation conditions, material supply and finished goods transport.
- Planned investment and schedule
- Total investment: RMB 350 million.
- Comparable applications
- Additive manufacturing factories; 3D printed product production bases; digital manufacturing parks.
China reference 25 · Energy and utilities
Biomass Boiler Conversion at a Heating Plant in Northeast China
Planned conversion of eight existing coal-fired boilers to biomass at a heating plant in Heilongjiang, together with building and ancillary facility alterations. This is a redevelopment of an existing site.
- Development approach
- Acquisition of an existing plant followed by boiler and building conversions.
- Key facilities
- Conversion of eight boilers, building alterations and heating network infrastructure.
- Key site requirements
- An existing heating plant in Daqing, Heilongjiang; fuel supply and the heat service area.
- Planned investment and schedule
- Total investment: approximately RMB 541 million. Construction period: 13 months.
- Comparable applications
- Biomass heating plant conversions; industrial boiler renewal; energy station development.
China reference 26 · Agricultural processing
Soybean Processing and Storage Logistics
Planned soybean processing facilities and associated warehousing and logistics, linking raw material receipt, processing and finished goods storage and transport.
- Development approach
- Development of soybean processing and storage facilities.
- Key facilities
- Raw material receiving, processing and finished goods warehousing facilities.
- Key site requirements
- Soybean aggregation and distribution, process energy demand and transport access.
- Comparable applications
- Soybean processing plants; grain and edible oil processing bases; agricultural product warehousing and logistics parks.
China reference 27 · Mining equipment and intelligent manufacturing
Intelligent Mining Support Equipment Factory in Northwest China
A planned intelligent mining support equipment factory in Ningxia, covering equipment production, automation and site infrastructure.
- Development approach
- Development of an intelligent mining support equipment factory.
- Key facilities
- Equipment manufacturing facilities, automation equipment and site infrastructure.
- Key site requirements
- Ningxia; suitability for large equipment production, transport and energy supply.
- Planned investment and schedule
- Total investment: approximately RMB 1.084 billion.
- Comparable applications
- Mining support equipment factories; intelligent coal mining machinery factories; mining equipment manufacturing bases.
China reference 28 · Biopesticides and chemicals
High-Efficiency Biopesticide Formulation Production
Planned production of 34,000 tonnes of high-efficiency biopesticide formulations per year, with formulation manufacturing and ancillary facilities.
- Development approach
- New biopesticide formulation production facilities.
- Key facilities
- Formulation production, storage and transport, and environmental and safety facilities.
- Key site requirements
- Chemical park admission requirements, environmental conditions and hazardous material management.
- Planned investment and schedule
- Total investment: RMB 1 billion. Construction period: 24 months.
- Comparable applications
- Biopesticide formulation factories; agrochemical formulation production bases; fine chemical plants.
China reference 29 · Non-ferrous metals and advanced materials
Gallium Metal Production
Planned production of 60 tonnes of gallium metal per year, covering metal extraction, processing and associated production facilities.
- Development approach
- New gallium metal production facilities.
- Key facilities
- Metal extraction and processing equipment and utilities.
- Key site requirements
- Feedstock availability, energy supply and environmental conditions.
- Planned investment and schedule
- Total investment: RMB 80 million. Construction period: 12 months.
- Comparable applications
- Gallium metal factories; rare and dispersed metal production bases; non-ferrous material processing projects.
China reference 30 · Environmental equipment
Intelligent Upgrade of Environmental Equipment Manufacturing
An intelligent upgrade targeting annual output of 70,000 sets of environmental equipment, focused on equipment and process renewal within an existing factory.
- Development approach
- Intelligent upgrading of existing environmental equipment manufacturing premises.
- Key facilities
- Intelligent production lines, factory alterations and an intermediate warehouse.
- Key site requirements
- Approximately 10,000 m² of existing factory space; production line conversion and material handling requirements.
- Planned investment and schedule
- Total investment: approximately RMB 185 million. Construction period: 16 months.
- Comparable applications
- Environmental equipment factory conversions; intelligent environmental equipment manufacturing; industrial equipment production line upgrades.
China reference 31 · Non-ferrous metals and resource recycling
Integrated Utilization of Copper and Nickel Smelting Slag
Planned integrated solid waste utilization facilities with capacity to process 6 million tonnes of smelting slag per year, including 1.8 million tonnes per year in Phase I.
- Development approach
- Phased development of smelting slag treatment facilities.
- Key facilities
- Slag receiving and treatment facilities and integrated solid waste utilization lines.
- Key site requirements
- Proximity to smelting slag sources; verification of transport, land and environmental conditions.
- Planned investment and schedule
- Total investment: RMB 650 million. Construction period: 24 months.
- Comparable applications
- Copper and nickel smelting slag treatment plants; industrial solid waste recovery bases; non-ferrous metal recycling projects.
China reference 32 · Automotive components
New Energy Vehicle Component Assembly Base
A planned new energy vehicle component assembly project, integrating assembly lines, warehousing and production support facilities.
- Development approach
- New assembly facilities for new energy vehicle components.
- Key facilities
- Component assembly lines, warehousing and testing facilities.
- Key site requirements
- Automotive supply chain connections and finished goods distribution access.
- Planned investment and schedule
- Total investment: approximately RMB 359 million.
- Comparable applications
- New energy vehicle component factories; automotive assembly bases; automotive supplier industrial parks.
China reference 33 · Modern agriculture and new energy
Integrated Agriculture Livestock and Solar PV Technology Park
A planned technology park combining agriculture, livestock production and solar photovoltaics, with an integrated layout of production, farming and energy facilities.
- Development approach
- Phased development of an integrated agriculture, livestock and solar PV park.
- Key facilities
- Agricultural and livestock production facilities, solar PV systems and shared infrastructure.
- Key site requirements
- Coordination of agricultural land use, solar resource conditions and grid connection.
- Planned investment and schedule
- Total investment: RMB 2.8 billion. Phase I: 2 years. Phase II: 1 year.
- Comparable applications
- Integrated agriculture, livestock and solar parks; controlled-environment agriculture bases; energy projects supporting agriculture and livestock production.
China reference 34 · Advanced chemical materials
Organosilicon Product Manufacturing
Planned organosilicon production facilities and utilities for the manufacture of advanced chemical materials.
- Development approach
- New organosilicon material R&D and production facilities.
- Key facilities
- Intelligent workshops, warehouses, laboratory testing and office facilities.
- Key site requirements
- Approximately 50 mu of planned land; suitability for chemical material production, safety and environmental requirements.
- Planned investment and schedule
- Total investment: approximately RMB 150 million.
- Comparable applications
- Organosilicon factories; silicon-based material production bases; fine chemical industrial parks.
China reference 35 · Food processing and cold chain
White-Feather Broiler Processing and Cold Chain Facilities in North China
Planned facilities in Hebei for slaughtering 120 million white-feather broilers per year, with 60,000 tonnes of cold chain logistics capacity, integrating poultry processing and refrigerated storage.
- Development approach
- Phased development of slaughtering, processing and cold chain facilities.
- Key facilities
- Slaughtering and cutting facilities, cold storage and logistics infrastructure.
- Key site requirements
- Hebei; live poultry supply, food hygiene and cold chain transport.
- Planned investment and schedule
- Total investment: approximately RMB 901 million. Development period: 4 years and 9 months.
- Comparable applications
- Poultry slaughter and processing plants; meat production bases; supporting cold chain logistics projects.
China reference 36 · Hydrogen energy and chemicals
Hydrogen Liquefaction Demonstration Facility in North China
A planned demonstration facility in Hebei with hydrogen liquefaction capacity of 1 tonne per day, including liquefaction process equipment and production safety facilities.
- Development approach
- New hydrogen liquefaction demonstration plant.
- Key facilities
- Liquefaction equipment, storage and transport facilities, and safety systems.
- Key site requirements
- Hebei; verification of hydrogen supply, energy demand and safety separation distances.
- Planned investment and schedule
- Total investment: approximately RMB 98.5438 million. Construction period: 12 months.
- Comparable applications
- Hydrogen liquefaction plants; hydrogen demonstration facilities; industrial gas production bases.
China reference 37 · Cold chain logistics
Completion and Expansion of Cold Chain Bases in Central and East China
Two cold chain bases in Zhengzhou and Kunshan, with planned building areas of approximately 115,000 m² and 88,000 m² respectively, including existing buildings and subsequent construction.
- Development approach
- Completion and expansion of existing cold chain bases.
- Key facilities
- Cold stores, warehousing, logistics and distribution facilities.
- Key site requirements
- Zhengzhou and Kunshan; connectivity with transport hubs and food cold chain networks.
- Planned investment and schedule
- Combined acquisition and follow-on construction investment: approximately RMB 1.134 billion. Follow-on construction period: 3 years.
- Comparable applications
- Cold chain warehousing bases; cold store completion and conversion projects; food cold chain logistics parks.
China reference 38 · Building materials and resource recycling
Integrated Utilization of Coal Gangue
Planned coal gangue treatment and resource recovery facilities, linking feedstock preprocessing, recycled product manufacturing and environmental infrastructure.
- Development approach
- New integrated coal gangue utilization facilities.
- Key facilities
- Solid waste preprocessing, recycled product production and environmental facilities.
- Key site requirements
- Proximity to coal gangue sources; verification of transport and environmental conditions.
- Planned investment and schedule
- Total investment: RMB 80 million.
- Comparable applications
- Coal gangue utilization plants; building material production from solid waste; circular economy projects in mining areas.
China reference 39 · Environmental materials and water treatment
Membrane Material Production Base
Planned factory buildings and associated facilities for the manufacture of water treatment membrane products.
- Development approach
- New membrane material production buildings.
- Key facilities
- Membrane product manufacturing, warehousing and utilities.
- Key site requirements
- Clean production conditions, water supply and wastewater treatment.
- Planned investment and schedule
- Total investment: approximately RMB 185 million. Construction period: 16 months.
- Comparable applications
- Water treatment membrane factories; environmental membrane material production bases; water equipment industrial parks.
China reference 40 · Modern agriculture
Ecological Agriculture Park
A planned ecological agriculture park with production, exhibition and supporting facilities. This is presented as a park development case, rather than a standalone manufacturing factory.
- Development approach
- Phased development of an ecological agriculture park.
- Key facilities
- Agricultural production and exhibition facilities, with staff amenities.
- Key site requirements
- An urban agriculture area in Beijing; suitable agricultural land and market catchment.
- Planned investment and schedule
- Total investment: RMB 410 million. Expected overall construction period: 2.5 years.
- Comparable applications
- Modern agricultural parks; controlled-environment agriculture bases; parks supporting agricultural processing.
China reference 41 · Medical devices and biopharmaceuticals
Diagnostic Reagent and Consumable Production Facility Conversion in South China
Planned fit-out and conversion of consumable and extraction reagent production departments in Guangzhou, improving production areas and associated facilities.
- Development approach
- Fit-out and conversion of production departments within an existing factory site.
- Key facilities
- Consumable and extraction reagent production areas and cleanroom infrastructure.
- Key site requirements
- An existing site in Guangzhou; reagent production, cleanliness and fire safety requirements.
- Planned investment and schedule
- Total investment: approximately RMB 12.0739 million. Construction period: 8 months.
- Comparable applications
- Diagnostic reagent workshop conversions; medical consumable factories; biopharmaceutical production facility upgrades.
China reference 42 · Agricultural processing
Sichuan Pepper Processing Demonstration Project in Northwest China
A planned Sichuan pepper processing demonstration project in Shaanxi, with facilities for raw material treatment, processing and product storage and transport.
- Development approach
- Agricultural processing workshop conversion and equipment installation.
- Key facilities
- Sichuan pepper preprocessing, processing and warehousing facilities.
- Key site requirements
- A Sichuan pepper growing area in Shaanxi; raw material collection, seasonal processing and logistics.
- Planned investment and schedule
- Total investment: approximately RMB 6.2933 million. Construction period: 12 months.
- Comparable applications
- Sichuan pepper processing plants; specialty agricultural processing bases; seasoning production parks.
China reference 43 · Metal processing and environmental services
Metal Surface Treatment Industrial Park in Southwest China
A planned industrial park in Guizhou with centralized surface treatment factory buildings, wastewater and waste acid treatment, and steam and gas infrastructure.
- Development approach
- New metal surface treatment industrial park.
- Key facilities
- Surface treatment workshops, centralized environmental treatment facilities and utilities.
- Key site requirements
- Guizhou; coordinated environmental treatment and shared utility provision.
- Planned investment and schedule
- Total investment: RMB 1 billion. Construction period: 2 years.
- Comparable applications
- Metal surface treatment industrial parks; centralized electroplating zones; industrial wastewater infrastructure.
China reference 44 · Metal materials
Metal Materials Industrial Park
A planned metal material industrial park combining processing, warehousing and ancillary facilities, including five metal component production lines.
- Development approach
- New metal material industrial park and production lines.
- Key facilities
- Five metal component production lines, warehousing and environmental facilities.
- Key site requirements
- Steel supply, heavy goods transport, gas supply and wastewater treatment conditions.
- Planned investment and schedule
- Total investment: RMB 100 million. Construction period: 1.5 years.
- Comparable applications
- Metal material industrial parks; metal processing bases; standard factory buildings for advanced materials.
China reference 45 · Food processing and cold chain
Intelligent Food Processing and Cold Chain Industrial Park in Central China
A planned park in Hunan integrating cattle and sheep slaughtering and cutting, food processing, a central kitchen and cold storage. Phase I covers approximately 184.47 mu, with approximately 113,400 m² of buildings.
- Development approach
- Phased development of a food processing and cold chain industrial park.
- Key facilities
- Slaughtering and cutting facilities, a central kitchen, R&D and production facilities, and cold chain warehousing.
- Key site requirements
- Hunan; livestock supply, food safety and cold chain transport conditions.
- Planned investment and schedule
- Total investment: approximately RMB 500 million. Construction period: 8 months.
- Comparable applications
- Meat processing parks; central kitchen factories; intelligent cold chain industrial parks.
China reference 46 · Grain and edible oil processing
Soybean Oil Processing Plant in East China
A planned soybean oil processing plant in Shandong on approximately 55 mu, with approximately 56,700 m² of buildings for crushing, refining, bottling and storage. Planned annual output is 50,000 tonnes.
- Development approach
- New soybean oil processing plant.
- Key facilities
- Crushing, refining and bottling lines, warehouses and supporting facilities.
- Key site requirements
- Qingdao, Shandong; inbound soybean logistics and distribution of edible oil products.
- Planned investment and schedule
- Total investment: approximately RMB 225 million. Construction period: approximately 2 years.
- Comparable applications
- Soybean crushing plants; grain and edible oil refining bases; edible oil bottling factories.
China reference 47 · Textiles and apparel
Garment Production and Distribution Center in East China
A planned center in Qingdao, Shandong, with approximately 49,000 m² of buildings for garment production, inspection and distribution, together with underground facilities.
- Development approach
- New garment production, inspection and distribution center.
- Key facilities
- Production buildings, inspection and distribution facilities, and underground ancillary space.
- Key site requirements
- Qingdao, Shandong; coordination of garment production, inspection and distribution.
- Planned investment and schedule
- Total investment: RMB 120 million. Construction period: 2 years and 3 months.
- Comparable applications
- Garment production bases; finished garment inspection and distribution centers; textile industrial parks.
China reference 48 · Food manufacturing
Food Industrial Park in East China
A planned food industrial park in Ningbo, Zhejiang, on approximately 150 mu, with approximately 281,100 m² of buildings for factories, cold storage, food R&D, offices and staff accommodation.
- Development approach
- New food industrial park.
- Key facilities
- Factory buildings, cold storage, food R&D facilities, offices and staff accommodation.
- Key site requirements
- Ningbo, Zhejiang; food production, cold chain warehousing and urban distribution.
- Planned investment and schedule
- Total investment: approximately RMB 1.502 billion. Construction period: 1 year and 6 months.
- Comparable applications
- Food industrial parks; bakery and dairy production bases; food cold chain infrastructure.
China reference 49 · Plastic products
Intelligent Injection Molding in South China
A planned project in Jieyang, Guangdong, on approximately 15 mu, with approximately 15,000 m² of intelligent injection molding workshops and service facilities. Planned output is approximately 10,000 tonnes of plastic packaging boxes and containers per year.
- Development approach
- New intelligent injection molding factory buildings.
- Key facilities
- Injection molding workshops, surface processing and testing facilities, and environmental and fire safety infrastructure.
- Key site requirements
- Jieyang, Guangdong; plastic raw material transport, energy supply and environmental conditions.
- Planned investment and schedule
- Total investment: RMB 120 million. Construction period: 12 months.
- Comparable applications
- Intelligent injection molding factories; plastic packaging production bases; injection molding industrial parks.